Is there a tcode for scheduling that "assigns" negative PABs to a scheduler's screen where they can decide to plan production for something in a certain time bucket (whether it is for a day or a week)?

Or is this done automatically? If so, could someone explain the process and next steps?

My thought process is there has to be something like this that is similar to MM-ME57 (Assign and Process Requisitions).

Please let me know; if my thought process is off then any corrections or explanations would be appreciated as well.

Thanks

0 Likes
View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

What is a PAB?

Regards,
Caetano

former_member775668
Discoverer
0 Likes

PAB = Projected Availiable Balance; determines whether or not to create a scheduled MPS receipt.