Dears,

customer requirement is to split the operation quantity between multiple work centers during dispatching.

e.g: the plant has 2 mixers one to process 600 kg in 1 hr while the other is to process 300 kg in 1 hr.

so, if an order with Quantity 900 kg it will be splitted between mixer1 (600 kg) & mixer 2 (300 kg).

the two mixers will have different formulas thus can't be maintained as individual capacities.

So, can we split order quantity between multiple work centers (& without formation of a child order split)

or, if I'll use individual capacity , can I incorporate a parameter that is individual capacity related in the formula for capacity & scheduling.

0 Likes
View Entire Topic
Former Member
0 Likes

Hi Moustafa,

1. Keep your work center having more than one capacity category

2. Go to Capacity header  mention No. of indiv. cap.=2.

3. Create header details for individual capacities from Goto -> Individual Capacities and maintain for 001, 002.

After the production order creation


4. Go to operation details, Choose "Cap. reqmt assignmt" tab select capacity 001 from list  assign 600 KGs, for 002 = 300 kgs  in split qty as required.


5. level this capacity using CM27, This levelling can be done by splits.

Check & Revert,

Ravisankar