What would you say is the amount of time it would take to implement CUP, in the simplest way possible? In other words, barring unforeseen circumstances, and with the simplest workflows, how long would it take?

Thanks a lot ...

Santosh

View Entire Topic
Former Member
0 Likes

Hi Santosh

I hope you have RAR installed in your system.

To implement CUP you can follow the plan below,

1. Compliant User Provisioning Implementation 14 days

2 Complete AE Pre-Implementation Checklist 1 day

3. Deploy and install AE on NW 1 day

4. Perform AE post -installation configuration and connectivity 1 day

5. Perform AE issue resolution 1 day

6. Discussion & Configuration of Test workflows 7 days

7. Run end to end request scenario testing for each workflow path 3 days

It is upto your project resource allocation and working hours to minimise the task ASAP.

Regards,

Sudip.