on ‎2008 Mar 21 5:15 PM
Hai,
If Anybody Knows User Acceptance Testing,Please define it and what's difference between User Acceptance Testing and unit/integration testing...
Request clarification before answering.
Unit and Intergration testing is done by the Developer and the functional guy, developer does the Unit testing to check if his codeis working properly,, and once all the development is done,, functional guy performs the Integration testing to see if the funcationality is alright and the all the objects are integrated properly to meet the business requirement.
UAT is done by the End user or the business user who actually will be using these applications, he will run few test scenarios and see if his business requirement are met or not..
let me know if you have further queries.
I hope you found this helpful
..
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please don't leave a question as a comment to a Former Member in a thread from 2008. No one will see your question this way. If you'd like to ask a question, please follow the guidance at https://community.sap.com/resources/questions-and-answers#How_to_ask_a_question. You may even link to this thread for context.
Kind regards.
--Jerry
| User | Count |
|---|---|
| 9 | |
| 7 | |
| 6 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.