on ‎2005 Jul 13 12:10 PM
Hello,
i have a problem with the "Update from PSA" Process in a Process Chain.
I am loading data from ODS A into ODS B.
The data is loaded via Delta Update into the PSA and should be then updated via a full repair request into ODS B.
(It is not possible to load the data via delta process into ODS B, because I deleted all data from the ODS and rebuilted it with full repair requests.)
It is manually possible to do this procedure, but it was not possible for me to figure out a way how to manage the procedure in a process chain.
Would be great if someone could help me.
Request clarification before answering.
If you do not load any other data providers from ODS A, you can repeat the whole process. You just have to delete the existing delta initialization in your init infopackage. After that you can do a new initialization.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.