on ‎2005 Jul 13 12:10 PM
Hello,
i have a problem with the "Update from PSA" Process in a Process Chain.
I am loading data from ODS A into ODS B.
The data is loaded via Delta Update into the PSA and should be then updated via a full repair request into ODS B.
(It is not possible to load the data via delta process into ODS B, because I deleted all data from the ODS and rebuilted it with full repair requests.)
It is manually possible to do this procedure, but it was not possible for me to figure out a way how to manage the procedure in a process chain.
Would be great if someone could help me.
Request clarification before answering.
If you do not load any other data providers from ODS A, you can repeat the whole process. You just have to delete the existing delta initialization in your init infopackage. After that you can do a new initialization.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oliver
Your uploading ODS B from ODS A?
If yes, then you cannt upload the data via PSA.
Please correct me if iam wrong in understanding.
Mention step by step how your uploading.
Regards,
Rohini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Upload looks like this:
ODS A ---> PSA ---> ODS B
From ODS A into PSA: Delta Update
From PSA into ODS B: Full Repair Update
The problem is, if i use the "Update from PSA" Process in the Process Chain it uses a Delta Process,
but I need a Full Repair Process.
The reason why I need a full repair request is that I deleted all data from ODS B, including the Initialize process and rebuilted it with full reqair requests.
Now if i am loading delta updates, i can not activate the request (in ODS B), because of the missing init request.
It is also not possible to load a full update request, because I also get a error message, when I try to activate the data. So a full repair requst is my only solution.
The easiest way would be to reconstruct the old initialize request and the following deltas, but
it would take to much time.
Hi Oliver,
After doing Full repair requests into ODS B, you can still continue with you Delta updates from A -> B by simply doing a Init Without Data transfer from A-> B which will help resume your Delta updates.
(If I understood correct, now you have all data from A into B and in future want to continue with the Delta updates into B from A forany change/addition in A)
Also, make sure you have updated B thru <b>Repair</b> requests and not just Full loads. Take a look at OSS note 689964 if you want to know more details on this.
Regards,
Sree
Regards,
Sree
| User | Count |
|---|---|
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.