Dear Guru's

As i am in need help regrading master data process chains.

I have requirement to create a master data process, where Sales Group, Division, Cross-distribution-chain material status, Sales office, plant, Distr Chnl and Billing block . These all should run monthly manner.

I searched in google and SCN but i didn't found relevant docs for master data process chains.

Please help me on this.

0 Likes
View Entire Topic
Former Member
0 Likes

hi Syam ,

try this process and check it if possible , might be it will work.

Failure has occurred as the no.of erroneous records are more than the value that was set in "Update tab". Follow below steps:

1.Change the setting to "Valid records update, reporting possible" and re-run the DTP by increasing the value for field "Maximum no.of errors per pack" (e.g:99,999)

2. Rerun the DTP

3. Now the error records will be available in error stack, Correct and update them to the target using error DTP.

4. Change the setting of Error handling to "No Update, No Reporting" else you may miss few records every time.

Go through the below document for complete details about error handling in DTP:

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/40baa0dd-cc27-2e10-b590-a7488f42f...