Dear gurus,
In my process order ,in scheduling the time is not being taken though we have maintained parameters in resource and recipe.
Can anybody help?
Request clarification before answering.
Hi,
Goto SPRO and do the below config.
Production -> SHopfloor Control -> Operations -> Scheduling -> Define Scheduling Parameters for the Order Type.
Goto the above node and select your Plant / Order Type / Prod Scheduler and double click ans goto detailed screen and config the Scheduling Control for detailed scheduling and provisde either Forward / Backward / Current etc.
Do the above config and check the Prod order scheduling and come back if reqd any.
regards
radhak mk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 13 | |
| 12 | |
| 6 | |
| 6 | |
| 6 | |
| 4 | |
| 3 | |
| 2 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.