Hi.
what's MRP Controller ?
how to create it.
when it's used.
regards.
ly
Request clarification before answering.
Hi,
-The MRP controller is responsible for all activities related to specifying the type,
quantity, and time of the requirements, in addition to calculating when and for what quantity an
order proposal has to be created to cover these requirements.
-The MRP controller needs all the information on stocks, stock reservations, and stocks on order to calculate quantities, and also needs information on lead times and procurement times to calculate dates.
-The MRP controller defines a suitable MRP and lot-sizing procedure for each material to determine procurement proposals.
-MRP controller can authorize any changes to the master plan before they
affect the various BOM levels.
Regards,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 57 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.