on ‎2008 Dec 17 5:41 AM
Hi.
what's MRP Controller ?
how to create it.
when it's used.
regards.
ly
Request clarification before answering.
Hi,
-The MRP controller is responsible for all activities related to specifying the type,
quantity, and time of the requirements, in addition to calculating when and for what quantity an
order proposal has to be created to cover these requirements.
-The MRP controller needs all the information on stocks, stock reservations, and stocks on order to calculate quantities, and also needs information on lead times and procurement times to calculate dates.
-The MRP controller defines a suitable MRP and lot-sizing procedure for each material to determine procurement proposals.
-MRP controller can authorize any changes to the master plan before they
affect the various BOM levels.
Regards,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
It is nothing but the authority to control the MRP process..all the mails for the procurement go though the MRP conrtroller...
You can define MRP controllers from SPRO >> MM >> CBP >> Master data >>Define MRP controllers...
It is defined per plant...
uses:
1. Used for missing part messages at GR
2. Its a receipient for mail
Hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
MRP Controller is a person or group of persons responsible for a group of materials in MRP in a plant or company.Material that takes part in material requirements planning must be assigned to an MRP controller.(Materials Planner)
MRP Controller can be defined in "OMD0"
mail receipient
thanks n regards
KKY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
MRP controller is the person who is responsible for plannig run in the plant or company.
You have to configure in plant parameters level.
The person responsible for a group of materials in MRP in a plant or company.
Material that takes part in material requirements planning must be assigned to an MRP controller.
path is
SPRO-IMG-Material management-Consumption-Based Planning-Plant parameters- Maintain
While creating material master you maintain MRP views in MRP 1 view you have to maintain that MRP controller.
Regards
Ravi Shankar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi...
Displaying Where an MRP Profile Is Used
Unless indicated otherwise, the information contained in this info object is relevant to the material master for industry and to the article master for retail. Retail customers are requested to substitute:
article for material
requirements planning for material requirements planning or MRP
site for plant
stock planner for MRP controller
Procedure
In the Material Master menu, choose Profile ® MRP profile ® Usage.
The selection screen appears.
Enter the name of the profile. You can also enter a plant and MRP controller to restrict the selection. Then choose Execute.
Result
A list is displayed of the material master records in which the MRP profile is used. You now have the following options:
You can display or change the MRP profile by choosing Display profile or Change profile respectively.
You can display or change a particular material master record in which the MRP profile is used by choosing Display material or Change material respectively. In the material master for industry, the MRP view on the material master record appears, from which you can access the other views. In the article master for retail, the Display or Change Article: Initial Screen appears.
regards............ Sri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 58 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.