cancel
Showing results for 
Search instead for 
Did you mean: 
Subscribe

Hi,

I f i mainatin GR processing time in material amster as 2 days. Then if i receive the goods for the same material after a week. Will system post Goods Receipt??. Can any one help me??

0 Likes
View Entire Topic
Former Member
0 Likes

Do you mean , after receving the goods, we have to post the Migo with in 2 days. After 2 days it doesn't accept. right.

csaba_szommer
Active Contributor
0 Likes

No, I'm just saying SAP uses the GR processing time for calculation. When you run MRP (MD01/MD02/MD03), SAP will consider the GR processing time as well.

If you need your product on 20th of December, you PDT is 10 days, your GR processing time is 2 days, SAP will calculate the lead time as 12 days. So, you should issue the PO at least on the 7th of December (20-12 ...maybe you should issue the PO one day before...).

GR processing time is just for this. You can do GR at any time, even on 8th of December, since these pieces of information (PDT, GR processing time) are just used in MRP calculation.

GR processing time HAS NOTHING TO DO WITH GR POSTING - please try it in your Sandbox system

Regards,

Csaba