I have booked 3 invoices for a particular vendor each with different payment terms. Say for example

1st one due on 10/03/2008

2nd one due on 19/03/2008 and the

3rd one due on 25/03/2008.

My client requirement is that on running F110 today (06/03/2008) they want 3 cheques to be printed each of them with their respective due date as cheque date.

Please let me know on how to proceed on this

Regards

Ganesh

0 Likes
View Entire Topic
Former Member
0 Likes

hi

better to go for f-58 t code