Hello all,

I want to do basic date scheduling for the planned order & production order.

I am selecting Scheduling type as Basic date scheduling during MRP run.

Also I have maintain Scheduling margin key(1day 1day 1day 1day) in material master.

when I run MRP & check the result, Scheduling is happened without considering the scheduling margin key.

So my question is "Does system consider Scheduling margin key during basic date scheduling or not...? "

If yes then does it have any configuration to consider Scheduling margin key during basic date scheduling?

Thanks & Regards,

Ashish Gunjal

0 Likes
View Entire Topic
DerekDing
Product and Topic Expert
Product and Topic Expert

Yes, the Float Bef. Prdn will impact the basic start date in the production order.

For example:

1. In this production order, Schedule Margin key = blank, which means = 0.

The start date = Requirement date - Inhouse date = 2023.09.25 - 2days= 2023.09.22

Requirement date = 2023.09.25

Inhouse date = 2 days

2. Then we set the Schedule Margin key = 001, Float Bef. Prdn = 2 Days.

The start date = Requirement date - Inhouse date - Float Before Production = 2023.09.25 - 2days - 2days = 2023.09.19

ashish_gunjal
Explorer
0 Likes

Thank you for the answer.

I think you are creating manual production order.

Is this possible by running MRP considering basic date scheduling?


Thanks