Hello all,
I want to do basic date scheduling for the planned order & production order.
I am selecting Scheduling type as Basic date scheduling during MRP run.
Also I have maintain Scheduling margin key(1day 1day 1day 1day) in material master.
when I run MRP & check the result, Scheduling is happened without considering the scheduling margin key.
So my question is "Does system consider Scheduling margin key during basic date scheduling or not...? "
If yes then does it have any configuration to consider Scheduling margin key during basic date scheduling?
Thanks & Regards,
Ashish Gunjal
Request clarification before answering.
Yes, the Float Bef. Prdn will impact the basic start date in the production order.
For example:
1. In this production order, Schedule Margin key = blank, which means = 0.
The start date = Requirement date - Inhouse date = 2023.09.25 - 2days= 2023.09.22

Requirement date = 2023.09.25

Inhouse date = 2 days

2. Then we set the Schedule Margin key = 001, Float Bef. Prdn = 2 Days.
The start date = Requirement date - Inhouse date - Float Before Production = 2023.09.25 - 2days - 2days = 2023.09.19

You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
According to the example, which is running MRP, and then transfer the planned order to production order, not create the production order manually.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 60 | |
| 30 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.