Dear All,
There are two production versions 0001 and 0002 for a finished material. When I create production order from planned order it automatically selects version 0001. If I want it to select version 0002 automatically what should I do?
Regards
Hammad
Request clarification before answering.
Hi,
U can do manually enter production version 0002 in change mode of Pld ord.
Regards,
S.Suresh.