Dear All,
There are two production versions 0001 and 0002 for a finished material. When I create production order from planned order it automatically selects version 0001. If I want it to select version 0002 automatically what should I do?
Regards
Hammad
Request clarification before answering.
Hi Hammad,
Try this , In material master go to prod version MRP 4 screen . Select prod version 1 and go to detail and in basic date select locked for any usage .
Neal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 12 | |
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.