Dear All,

There are two production versions 0001 and 0002 for a finished material. When I create production order from planned order it automatically selects version 0001. If I want it to select version 0002 automatically what should I do?

Regards

Hammad

View Entire Topic
Former Member
0 Likes

Hi,

Production Version selection is based on

1. Lot size

2. Validity

If these two are same both the PVs then system will select by default the first one.

look into these and change the parametrs so that system will select the 2nd PV.

otherwise do the customization settings in OPL8 for the Plant and order typ combination.

As Production Vesrion : 1 Manual Selection

Regards,

Siva