cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Automatic Production Version Selection

Former Member
5,321

Dear All,

There are two production versions 0001 and 0002 for a finished material. When I create production order from planned order it automatically selects version 0001. If I want it to select version 0002 automatically what should I do?

Regards

Hammad

View Entire Topic
Former Member
0 Likes

Hi Hammad,

As per your querry, you want production version 0002 should be selected automatically when you create production order instead od PV 0001. If you want PV 0002 should be selected automatically then,

1. Maintain lot size of of PV 0002 to quantity which you usually use for the production. So when you create production order system will use PV0002 based on lot size.

2. Or change validity period of PV0001 to a date which is outside the planning period. So it will be no longer valid in the period in which you are creating production order.

3. As specified by experts, you can change PV selection to manual by going to transaction COR4. And change selection of PV to manual selection for your order type or you can change it by going to transaction MM02. Then lock production version by selecting locked for any usuage.

Hope this resolve your issue, please reward if it is usefull.

Regards,

Avinash.

Former Member
0 Likes

Dear All,

Thanks for help. My problem is resolved.

Best Regards,

Hammad