Hi Guys,

I have set up the system to check for material availability when a production order is created, and again when it is released.

But I want the system to check material availability for all open production orders in the system periodically. Maybe once a day or once an hour. I do not want to go into mass processing, select these orders and then click on Availability check. It should automatically do an ATP check.

I am trying to setup a background job. But i feel something I am doing is wrong. I do not see the system running this check. Can someone please give me the steps of setting this job.

Thanks in advance.

0 Likes
View Entire Topic
Former Member
0 Likes

Hello,

Can you tell me how did you set up the system to check for material availabilty, for each planned order created ?

Is it working in every kind of creation (MD11, MF50, ...) ?

Thanks for your help.