‎2006 Oct 16 5:21 PM
i am new to abap, plz help me
if u can write select statement.
=========Logic for calculating daily production glazer fault incentive =========
===== === Calculate the total no. of piece fired in the month by glazing dept ========
Total No. Of Piece Fired = sum (ZHRT_PR_TRAN_002-ZZGLAZED_QTY) from ZHRT_PR_TRAN_002 for ZHRT_PR_TRAN_002-ZZDATE within Start Date and End Date from the Screen
Total No. of faults = COUNT(ZPPT_TRAN_002-ZZDECISION = REF,REW,PIT &&
ZPPT_TRAN_002-ZKODE1 = WAVY,THIN,SPAN,CRAW) from ZPPT_TRAN_002 for
ZPPT_TRAN_002-VERID = 1001 or 1002and ZPPT_TRAN_002-ZDOENTRY within Start Date and End Date from the Screen
Dept Fault% = Total No. of faults/ Total No. Of Piece Fired*100
===========Pick the Fault Slab Amount from ZHRT_MAST_006 ==============
If ZHRT_MAST_006- ZZDEPT =GLAZING and ZHRT_MAST_006- ZZEMP_CATEGORY = GLAZER then
{
if Dept Fault% >= ZHRT_MAST_006-ZZSLAB1L && <= ZHRT_MAST_006- ZZSLAB1H
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB1_AMT
Else if
Dept Fault% >= ZHRT_MAST_006-ZZSLAB2L && <= ZHRT_MAST_006- ZZSLAB2H
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB2_AMT
Else if
Dept Fault% >= ZHRT_MAST_006- ZZSLAB3L && <= ZHRT_MAST_006- ZZSLAB3H
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB3_AMT
Else if
Dept Fault% >= ZHRT_MAST_006- ZZSLAB4L && <= ZHRT_MAST_006- ZZSLAB4H
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB4_AMT
Else if
Dept Fault% >= ZHRT_MAST_006- ZZSLAB5L && <= ZHRT_MAST_006- ZZSLAB5H
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB5_AMT
Else if
Dept Fault% >= ZHRT_MAST_006- ZZSLAB6L
then
Fault Incentive Per Day = ZHRT_MAST_006- ZZSLAB6_AMT
Else
Fault Incentive Per Day = 0
}
‎2006 Oct 16 5:29 PM
Populate the start and end date into sdate range.
SELECT sum(ZHRT_PR_TRAN_002-ZZGLAZED_QTY) into lfired
from ZHRT_PR_TRAN_002
where zzdate in sdate.
SELECT Count(ZZDecision) into lfaults
from zppt_tran_002
where zdoentry in sdate
and zzdecision in ('REF','REW','PIT') and
zkode1 in ('WAVY','THIN','SPAN','CRAW').
lfperc = lfaults / lfired.
lfperc = lfperc * 100.
As for the second part you can read the data into internal table and use the CASE statement on lfperc field.
Message was edited by: Anurag Bankley
‎2006 Oct 17 5:56 AM
see it as to be done for all the records in the table
plz help me in declearing the loop.
‎2006 Oct 17 8:57 AM
The select statement would sum all the records in the table. As for loop do you mean the second part of your requirement ?
Regards