on ‎2009 May 11 6:28 AM
Hi,
We have configured CC 5.3 and we have scheduled Batch Risk Analysis for Role Analysis with Management Reports option. But this job is running from long time and there is no update.
Later we have scheduled one more job only for Z Roles sync by cancelling above mentioned job. But this job is also running from long time and it is running for all the roles other than Z Role also when we checked the Result.
Can you please advice me how we can do the first time sync in GRC CC for updating Management Report in lees time.
Thanks & Regards,
KKRao.
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi Rao,
Create an Index for the table VIRSA_CC_PRMVL and check the performance. Pls refer to the note 1044174.
Thank You
Regards,
Karthik