A while ago, I asked a question related to the different behaviour of version compare in SE38 after we had upgraded from NW750 SP07 to NW750 SP13 (EHP8). The RFC-connections needed for version compare have been closed off to generally prevent RFC-access from dev to prod for security reasons.

I looked through the security information provided in this guide, but didn't find specific enough recommendations there. And earlier questions in SAP Community don't quite match our current situation.

We have the rule in our development guidelines that version comparison between DEV and PROD should be done before new development gets started for an object. This obviously needs to be possible to do as easily and quickly as possible as it otherwise just won't get done.

I therefore have the following questions:

  • Do you routinely use version compare from DEV to PROD for workbench objects to e.g. ensure that all earlier changes have already made it into PROD or are there other/better options to do this?
  • How large is the risk of unauthorized activities in PROD if version compare is done via the standard functionality offered by the ABAP Workbench i.e. via SE38/SE80/SE39/SE11 for which RFC-connections need to be set up?
  • How can this risk be eliminated?
  • Are there recommendations of how RFC-connections and authorizations for version compares between DEV and QA/PROD should be defined or should they just not be defined at all?
  • Would setting up a separate client in PROD which then only contains client independent workbench-objects be helpful and could it be used for version compares?
  • Is there a means to do this easily and safely via Eclipse? (* see footnote below)

Thanks for any feedback - or even additional questions I haven't thought of yet!

Cheers

Bärbel

(*) Footnote: As of right now, Eclipse is not yet used much if at all and most development work happens via SAP GUI and the workbench transactions. When I tried a remote compare between the program versions in DEV and QA it sort of worked but several false hits where reported where e.g. the German Umlaut "ä" in my name was "butchered" in the displayed QA-code (as if the retrieval had a Unicode-issue). The fact, that Eclipse is in edit-mode by default is also a bit of an issue (I think).

View Entire Topic
chaouki_akir
Contributor

"Do you routinely use version compare from DEV to PROD for workbench objects to e.g. ensure that all earlier changes have already made it into PROD or are there other/better options to do this?"

Yes I do it, now and before. For me it is normal to have this possibility because as you said : "version comparison between DEV and PROD should be done before new development gets started for an object."

"The RFC-connections needed for version compare have been closed off"

What is the name of these RFC-connections ? I debugged and in my system and the is like [email protected]

"How large is the risk of unauthorized activities in PROD if version compare is done via the standard functionality offered by the ABAP Workbench i.e. via SE38/SE80/SE39/SE11 for which RFC-connections need to be set up?"

For me, the risk is that the developer is able to call from DEV, RFC enabled function modules. But user in PROD, should have lesser authorized objects.