Hi,
In the app Requirements Management we create a Work Package (without requirement). We can assign the project, but there is no wave available in the value help.
We have the same behavior in the My Work Package App. While creating or editing a workpackage we also cannot assign a wave.
The corresponding release is in status "PREPARE". The project, the phase and the waves are in status "released".
Can someone tell me why we cannot assign a wave?
Thank you,
Alexandra
Request clarification before answering.
Hello,
I had the same issue for SolMan SP14 with FB 200 SP 9.
Implemented SAP note 3156066 and it works.
Best regards!