Steps to change the source system for the data source

05-18-2015 9:03 AM
9966 views 10 comments Go to solution
0 Likes
SAP Managed Tags
Subscribe

Hi Experts,

Whenever I am double clicking the Info package to execute the load, the info package is not displaying and instead the error message is showing

Source system PCLNT200 is incorrect; not possible to load data.

Actually source system name is QCLNT100. Now if we change the source system name from PCLNT200  to QCLNT100 for this data source, then the problem will be resolved.

Can you guide me the steps to change the source system name for the data source.

Thanks,

Suresh.

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

former_member227168
Participant
0 Likes
Former Member
0 Likes

Hi Ram,

Thanks for your reply and the document...

I am expecting the steps to change source system for some data sources not for all.

Can you guide me with the steps for the same.

Thanks,

Suresh.

RamanKorrapati
Active Contributor
0 Likes

Hi Suresh,

first we need to maintain logical mappings(BDLS,
SM59) between required source and bw system.

check table - RSLOGSYSMAP

Tx - RSLGMP to change logical mappings.

Later you can replicate data source from source to bw and activate data source at bw side.

rest of the steps you might be known at bw side.

At which environment your facing this issue?

Quality or dev?

Thanks

Former Member
0 Likes

Hi Ram & Phani,

Thank you very much to your help.

Kind Regards,

Suresh.

Answers (2)

Answers (2)

Former Member
0 Likes

Hello Suresh,

I am facing same issues like you can you please guide me to resolve the same.

In my case for some datasource i am able to see production entries as source system like P6KCLT060.

please help.

thanks,

Nishant Rana.

Former Member
0 Likes

Hi Nishant,

Activate the data source at BI side.

Thanks,

Suresh.

Former Member
0 Likes

Hi Nishant

run BDLS it will resolve the errror

Former Member
0 Likes

Hi Suresh and SAI p,

I have already triggered BDLS conversion.
and data source is already activated in BI system.

is there any alternative to resolve this issues.

for you guys how your issue got resolved.?

thanks,

Nishant Rana

KodandaPani_KV
Active Contributor
0 Likes

Hi,

first check the how many source systems in BW system.

go to the RSA1 -> select the PCLNT200 -> right click -> check -> ok.

same thing to do another source system for QCLNT100

if are getting any error there please check the basis team.

if not getting any errror there use the same source system.

-Phani.

Former Member
0 Likes

Hi Phani,

Thanks for your quick reply..

Actually we have only one source system QCLNT100 for the BW Quality.

The source system PCLNT200 , this is the source system for the BW production. Recently we have don the system copy from BW production to the BW quality.


Now for some of the data sources in the BW quality, source system name showing correctly as  QCLNT100 and for some of the data sources in BW quality the source system name showing wrongly as PCLNT200.


In this case can we do any changes at BW side to correct the same.


Thanks,