Hello friends,

We have a problem. Now we have a new test system QA2. From BW system source system connection was configured for older test source system QA1.

We needed to route this source system to new system. I tried with changing RFC of QA1 to QA2 details.

Now, when i check RSA1 source system Check for QA1, i get this error :

Port 'A000000103 ' of type 'ALE ' does not exist

No destination exists to source system QA1

I can see this source system in RSA1 in BW. However, in WE21 port is not available now.

Please suggest.

I do not have to lose transfer rules/PSA tables..etc.

thanks

ashish

View Entire Topic
Former Member
0 Likes

Hi,

You have to create new source system for this. Its not possible to change source system by just changing RFC and restoring.

Thanks

Sunny

Former Member
0 Likes

Hello Sunny,

Dont be habe any option like logical name conversion or something like that.. what if i change QA2 to QA1 in RSBASIDOC as i have entry in it.

In this case what should be done for customizing done for older system..like transfer rules/PSA tables.

thanks

ashish

Former Member
0 Likes

You cannot change source system name in RSA1 by running BDLS. This is to change logical name of the client.

Thanks

Sunny

Former Member
0 Likes

Hi,

You have to run the BDLS conversion first and then setup the ports in we20 & 21. Also you have to update the port details & destinations in your other source systems.

Regards,

Vamshi.

Former Member
0 Likes

Hi Vamshi,

Can you please tell me in little more details please.

thanks

ashish

Former Member
0 Likes

Hi Vamshi,

I assigned a new port to QA1 partner profile and now i am only getting error :

No destination exists to source system QA1

How should i fix this..

thanks

ashish

Edited by: ashish vikas on Jun 23, 2011 3:00 PM

Former Member
0 Likes

Hi,

If you take this approach, you might get problems in Infocube settings.

Thanks

Sunny

Former Member
0 Likes

Hi Sunny,

Can you please tell me any standard method how we can transfer all development what was done for QA1 can be tranafered to QA2..

thanks

ashish

Former Member
0 Likes

You can have a look on SAP note 140276.

Thanks

Sunny