on ‎2010 Feb 11 4:53 AM
In RSPC, I have 15 Process chain.
1) How do I know which one is running and which one is not?
2) How do we know if the Process Chain is finished running successfully, including what time it complete?
3) Also, is there a way for us to see the number of records being extracted?
Please advise, thank you.
Request clarification before answering.
Hi,
In RSPC, double click the process chain for which you want to check the details.
click on the log button which you can see on the top.
1) iIf the log is green, then PC is finished succesfuly and you can see the time of execution there.
2)If it is still running, the log will be yellow and to check which step is running, see the process chain. the executing step will be in yellow colour.
3)to check the number of records extracted, right click on the process (info package or DTP) and click on process monitor.
THe other way is to use RSPCM. it is tool to check the status of all the process chains at once.
Thanks and Regards,
Srianth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi all,
Thanks so much for you input.
Is RSPCM only available in BI 7? We are on BW 3.5 only, what other way then?
My PC will call more than 29 InfoPackage. Instead of going the InfoPackage one by one to see the number of record extracted, is there a way to see the total number of records being extracted?
Please advise, thank you.
| User | Count |
|---|---|
| 8 | |
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.