Hi experts

I have a similar requirement as described in this blog:

http://scn.sap.com/thread/2091800

Process chain must be started between 08:00 and 16:00 on an hourly based period.

We have not understood how to schedule the event which is in the start variant of the process chain:

How do we trigger the process chain every hour in the daily time frame?

Thanks

0 Likes
View Entire Topic
RamanKorrapati
Active Contributor
0 Likes

Hi Thomas,

Why you need to go on event basis? is there any mandatory/dependences?

if not then we can handle it your issue with without much  hassle.

Lets assume it as you need to run your job hourly once from 8AM to 4PM and your chain will take 40mts every time.

if yes then just create a 8 jobs and schedule them on daily basis.

First job need to run at 9AM - daily

next one 10 AM- daily,   go on upto 4pm , like that way you can schedule your jobs on daily basis.

Thanks

Former Member
0 Likes

Yes, you are right. I know this.

But would like to test variant by alternative in the chain.

Thanks a lot.