Hi experts
I have a similar requirement as described in this blog:
http://scn.sap.com/thread/2091800
Process chain must be started between 08:00 and 16:00 on an hourly based period.
We have not understood how to schedule the event which is in the start variant of the process chain:
How do we trigger the process chain every hour in the daily time frame?
Thanks
Request clarification before answering.
Hi Thomas,
If you don't want to create a process chain. You can simply schedule same process chain in different timings. Say one schedule for 8:00 AM. One for 9:00 AM .. and so on until 16:00.
Hope this helps.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.