Dear All,

I've designed a "Process Chain" few months ago and its executing perfectly as it has been scheduled for daily execution @ 6:30: 00 a.m. Now, I have a need to modify it with the addition of two DTPs, one loads the delta data from DataSource to a new DSO and other loads the delta data from New DSO to a new InfoCube. I do not want to create new Process Chain for uploading to new DSO and InfoCube. I would like to use this existing "Process Chain". See below screen shot:

1. What is the above "Unknown Job" all about, when I click the check icon it disappear, but again it comes back? How to get rid of it?

2. How am I add new Delta DTP by "Mouse Right Click" and then use Connect to property and select the new Delta DTP?

3. After the addition of two Delta DTPs, do I need to only activate this Process Chain and no need to "schedule" it again?

4. What are the precautions to be taken care of while modifying an existing "Process Chain"?

I will appreciate your reply a lot.

Many Thanks!

Tariq Ashraf

0 Likes
View Entire Topic
Former Member
0 Likes

Hi Tariq

1. What is the above "Unknown Job" all about, when I click the check icon it disappear, but again it comes back? How to get rid of it?

Dont remove the link from one step to another unless you have connected your new objects. This issue appears when the object dependency is not found. Righ click on unknwon Job> scheduled jobs and delete it

2. How am I add new Delta DTP by "Mouse Right Click" and then use Connect to property and select the new Delta DTP?

Add your new DTPs from the process types and then link to the appropriate steps in the process chain

3. After the addition of two Delta DTPs, do I need to only activate this Process Chain and no need to

"schedule" it again?

You will need to save and activate the process chain again. After activation right click on start variant>Scheduled job>check if there is a release jobs as per your requirement

Thanks

Abhishek Shanbhogue