Dear All,

I've designed a "Process Chain" few months ago and its executing perfectly as it has been scheduled for daily execution @ 6:30: 00 a.m. Now, I have a need to modify it with the addition of two DTPs, one loads the delta data from DataSource to a new DSO and other loads the delta data from New DSO to a new InfoCube. I do not want to create new Process Chain for uploading to new DSO and InfoCube. I would like to use this existing "Process Chain". See below screen shot:

1. What is the above "Unknown Job" all about, when I click the check icon it disappear, but again it comes back? How to get rid of it?

2. How am I add new Delta DTP by "Mouse Right Click" and then use Connect to property and select the new Delta DTP?

3. After the addition of two Delta DTPs, do I need to only activate this Process Chain and no need to "schedule" it again?

4. What are the precautions to be taken care of while modifying an existing "Process Chain"?

I will appreciate your reply a lot.

Many Thanks!

Tariq Ashraf

0 Likes
View Entire Topic
Former Member
0 Likes

Hi,

1) Transport the new DSO and new Cube including the dependent objects from dev system to quality and then to production.

2) Then go to change mode of the existing process chain in dev system, add the the delta DTP to the new DSO as usually by selecting the process types

3) join the DTP according to your required position in the above chain by linking the  DTP process type. After this add the DSO activation step for new DSO.

4) Delete the indexes step for new cube

5) Add the DTP variant from new DSO to new cube

6) Add create indexes step for new cube

7)Now activate the process chain and then transport it to Production.

8)Again schedule the process chain to run at 6.30 am similar to how it was earlier in Production

Once your daily load is done, and before the next laod starts if you can move these transports successfully to production, no need to remove the process chain from Schedule, else it will run the old chain itself, but still once the Process chain is moved to Prod system, schedule it and then activtae it

( Removing from Schedule: RSPC-> Required Process Chain->Change mode-> Menu->Execution->Remove from Schedule)

If you want to change the chain directly in Production(though not recommended) follow the above steps by removing the chain from schedule. Once the changes are done, reschedule it and then activate it

Regards,