cancel
Showing results for 
Search instead for 
Did you mean: 
Subscribe

We've just copied the BW Production system onto a new server (Test BW).

The BW Production is pointing to Production ECC6.

We're have created a new RFC in the Test BW, which point to Test ECC system.

We have also perform the source system conversion via BDLS.

In RSA1 ->Source System, I can see name of the source system has been changed to Test ECC6.

However, when I right click on Source System ->Connection Parameter, I can see that

the Source System is still linked to the old RFC which is pointing to the Production ECC6.

How can I change this RFC so that it is pointing to the new RFC that we just created?

Please help, thank you.

0 Likes
View Entire Topic
pmoh
Participant
0 Likes

no answer

Former Member
0 Likes

thats not an error. even we got the same message and after we deleted and created the connection again it worked fine.

pmoh
Participant
0 Likes

Ananda,

thats not an error. even we got the same message and after we deleted and created the connection again it worked fine.

The problem is like I says, if we delete the Source System, all the Datasource, InfoSource etc of the existing data modelling will be gone correct? (This is the scary thing that I dont dare to try as I am not sure...)

So if I delete it and re-create the source system, then perform Activate and Replicate, will it link back again?

Is this what we should be doing?

Please advise, thank you.

Edited by: lynn on Mar 11, 2010 1:58 AM

Former Member
0 Likes

Hi,

Is that ok to modify the table RSBASIDOC manually ? Is there an existing transaction for that ?

regards,