We've just copied the BW Production system onto a new server (Test BW).

The BW Production is pointing to Production ECC6.

We're have created a new RFC in the Test BW, which point to Test ECC system.

We have also perform the source system conversion via BDLS.

In RSA1 ->Source System, I can see name of the source system has been changed to Test ECC6.

However, when I right click on Source System ->Connection Parameter, I can see that

the Source System is still linked to the old RFC which is pointing to the Production ECC6.

How can I change this RFC so that it is pointing to the new RFC that we just created?

Please help, thank you.

0 Likes
View Entire Topic
Former Member
0 Likes

Hi Lynn,

Pls do the following:

1) Go to SPRO --> 'Change source system name after transport'.

2) Enter the OrSource System as <ECC Production SS> and point the Target source system to the <New R/3 Source system>.

3) Reimport the Transport.

Hope this helps.

Regards,

Shrey