We've just copied the BW Production system onto a new server (Test BW).
The BW Production is pointing to Production ECC6.
We're have created a new RFC in the Test BW, which point to Test ECC system.
We have also perform the source system conversion via BDLS.
In RSA1 ->Source System, I can see name of the source system has been changed to Test ECC6.
However, when I right click on Source System ->Connection Parameter, I can see that
the Source System is still linked to the old RFC which is pointing to the Production ECC6.
How can I change this RFC so that it is pointing to the new RFC that we just created?
Please help, thank you.
Request clarification before answering.
Hi Lynn,
Pls do the following:
1) Go to SPRO --> 'Change source system name after transport'.
2) Enter the OrSource System as <ECC Production SS> and point the Target source system to the <New R/3 Source system>.
3) Reimport the Transport.
Hope this helps.
Regards,
Shrey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 10 | |
| 5 | |
| 5 | |
| 5 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.