Guys,

Help me out for the below Issues. No Clue what's the problem is going on.

1. Meta Chain Log View

2. When I Check "Display Variant"for "Master PC" Local Chain its successful.




3. When Checked the Background Tab for Master PC

0 Likes
View Entire Topic
Former Member
0 Likes

Hi,

it looks like steps inside meta chain executed successfully, however the meta chain process raised an event for the next process . Isin't the customer register header chain running?

Former Member
0 Likes

it looks like steps inside meta chain executed successfully, however the meta chain process raised an event for the next process . Isin't the customer register header chain running?

Customer Register is not running, because of Master PC is in Yellow Status

Former Member
0 Likes

Right click on Master PC-->choose "display message" --> click on tab 'chain'  , did you see status as undefined like below image   ?

Former Member
0 Likes

Jyothi,

Now i scheduled the meta chain for today's Date . So i am waiting for Master PC

Former Member
0 Likes

Once i activated and scheduled manually,

its working fine now.