Hi All

I would greatly appreciate it if you could assist me with the following issue that I am having at a customer. We are implementing Incident and Problem Management for Solution Manager 7.1 SP8. When we create a follow on (Problem) from the incident and close the problem ticket, it doesnt update the incident or close the incident.

We are using the SAP standard actions and conditions. This is the error we are receiving.

Thank you for your assistance.

Regards

Deena Govender

View Entire Topic
former_member204161
Active Participant

Hi Deena ,

As per standard , when a Problem gets created from the Incident, the Incident can be "locked " to it , so that it cannot be individually closed unless the Problem is closed first  . Now that the Problem is confirmed , you need to confirm the Incident manually.

Let me know if this helps.

Regards,

Shaswat

Former Member
0 Likes

Hi Shaswat

Thanks for the input. This really doesnt help me as the information I have been reading says that when you close a problem this will automatically confirm the incident. As you can see from the above screenshot, there is a predefined action that updates the statuses of the incident (lock/unlock...closed/completed).

I am assuming that this action will update the necessary incident accordingly.

Regards

Deena Govender

Former Member
0 Likes

Hi Deena,

I have tested in my system and is working fine.

When you confriming Problem - related Incidents are set to Solution Proposed

Rg Dan

Former Member
0 Likes

Deena Check this:

Action Update Dependent Incicidents

  1. Incidents can be set to Proposed Solution - check in wich statuses they are
  2. Is text id Solution is filled in problem ?
  3. Any attachments ?
  4. Related Knowledge articles in problem
  5. SAP notes ?

I have tried in my system same SP08 all is ok

  1. Created problem directly not as follow up
  2. Created incident and set status to In process
  3. Inserted Incident in Related incidents ass. block in problem
  4. Locked the incident
  5. Confirmed Problem
  6. Incident status updated - Solution Proposed

RG Dan

Former Member
0 Likes

Hi Dan

thank you for your assistance. I have tested as you have suggested and it works. Once the problem is closed, the statuses of the incident is updated and confirmed as well.

I am going to test creating a follow on problem document and see if this also works. Will get back to you shortly.

Regards

Deena Govender