Implementation project - ChaRM configuration

Former Member
0 Likes
769

Hi Expert,

I need some clarification,

if it possible to configure ChaRM for Dev-> QAS -> virtual PRD system.

Because currently PRD system in bulid state.Client expect to configure ChaRM for implementation phase for QAT testing.

So we have only Dev and QAS system in landscape.PRD bulit take some time to bulid.

So we are planning to configure ChaRM through Dev-> QAS -> virtual PRD system.it will work?

Please sugguset your comment for virtual PRD system use.

Rg,

Karthik

View Entire Topic
Former Member
0 Likes

Hi,

Why not go for two tier landscape and use CHARM. It will work too.

You will need to modify for the ToC to not move into QAS directly when RD is in "in testing". This is explained under SAP note 1419150.

SAP note 1690362 also

Regards,

KK.

Former Member
0 Likes

Hi KK,

Currently Production not yet ready. So i am planned to use virtual system.

If i use two system landscape, not able to Move the TR to PRD system.

So we are planning to configure ChaRM through Dev-> QAS -> virtual PRD system.it will work?

Please give some step to add virtual system.

Rg,

karthik

Vivek_Hegde
Active Contributor
0 Likes

Hi Karthik,

You can always add a new system to existing task list. Once your Prod build is done then include the system in the current tasklist.This is possible