on ‎2012 Mar 28 6:54 AM
Hi Expert,
I need some clarification,
if it possible to configure ChaRM for Dev-> QAS -> virtual PRD system.
Because currently PRD system in bulid state.Client expect to configure ChaRM for implementation phase for QAT testing.
So we have only Dev and QAS system in landscape.PRD bulit take some time to bulid.
So we are planning to configure ChaRM through Dev-> QAS -> virtual PRD system.it will work?
Please sugguset your comment for virtual PRD system use.
Rg,
Karthik
Request clarification before answering.
Hi,
Why not go for two tier landscape and use CHARM. It will work too.
You will need to modify for the ToC to not move into QAS directly when RD is in "in testing". This is explained under SAP note 1419150.
SAP note 1690362 also
Regards,
KK.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi KK,
Currently Production not yet ready. So i am planned to use virtual system.
If i use two system landscape, not able to Move the TR to PRD system.
So we are planning to configure ChaRM through Dev-> QAS -> virtual PRD system.it will work?
Please give some step to add virtual system.
Rg,
karthik
| User | Count |
|---|---|
| 9 | |
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.