Hello all,
During NetWeaver 7.4 upgrade from SPS5 to SPS9 on our consolidation system in step 5.5 Pre-processing, I've got below error:
I've tried to repeat that action but it did not help. In previous week I've finished exactly the same upgrade on development system and I did not have any
problems. For now I have no clue why it is does work. If it is upgrade fault or might be problem on sybase side.
In logs I've seen something weird:
"Error while setting identity property for column C""RR_ID of logging table /1CRR/LT00001387"" "" "' raised".
It seems that table above can not be activated, I've spoke with our DBA's and they claimed that for them DB looks OK .....
If someone will have any solution I will be grateful.
Thanks in advance for your support.
Regards,
Karolina Plebanek
Request clarification before answering.
Have you checked the job logs on what it says.
Please upload your SUM logs for this phase.
Also, share your system OS/DB version details.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.