on ‎2008 Jan 21 3:56 AM
Hi Everyone,
This is regarding Client Copy Using Client Export/Import Method. We have two system Production and Development system. Iam planning to do a client copy from from PRD to DEV. I know most of the steps to perform Client Copy.I have some doubhts So if some one can please help me out i would really appreciate it.
!) I want to know which user should be used to perfrom Client Export ?
2) I want to know know which user to be used to perform Client delete?
3) Is there any particular USER who is recommended to perform Client Copy or any USER can do it?
4) After the Client Delete Procedure thorugh SCC5 ..to get back the client space we do Reorganization ? can anyone plzz tell me what are the tables that i need to reorganize or if anyone can provide me the steps for Reorganization i would be really thankful.
Waiting For your Replies
Best Regards
Request clarification before answering.
Hello,
I am working with sap 4.7ee 620kernal
I am not able to work with BRTOOLS. can any one help me out to solve the issue.
Regards,
Sateesh J
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohammed,
so, I would go and reorganize all the tablespaces of your database. From my experience, when we had to do , we were getting an outage time (Saturday) in order to reorg through SAPDBA and by selecting all Tablespaces since there were client specific objects/table spread on all Tablespaces.
Rgds,
Loukas
| User | Count |
|---|---|
| 9 | |
| 7 | |
| 5 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.