Hello Team,
We are planning for EHP upgrade,to list out the impact business process we are planning to implement BPCA.
I am trying to run BPCA in the system RS1,i selected EHP option in step 1 and in the step 3 i could not see any recommended support packages under support package name.
Am i missing some thing? could someone guide me.
Do i need to run TBOM before BPCA?
Could someone share document if you have any for configuring BPCA.
Request clarification before answering.
Hello Sandeep,
Yes, You have to create TBOM first before using BPCA. Please activate UPL and create Semi Dynamic TBOMs and the try to run BPCA.
Also As Jan explained, please use SEA functionality which is specially prepared for implementing EHP or Service packs.
Thanks
Gaurav Patel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.