Hello Experts,

I am trying to setup a weekly schedule for a comm. channel in PI using the Availability Time Planning. This channel should run on Tuesday, Wednesday, Thursday and Friday every week. The following mentions what I have done :

I have selected the 'Weekly' schedule type. I have specified the time from 20:00 for 6 hours. I have also selected the days respectively. However, I am a bit confused on what to enter in the field - 'All : ______ weeks on ". I tried to specify '999 weeks'. The schedule works for the first week but does not work for the subsequent weeks.

How do I make it run on a weekly basis ? Am I missing something ? Please help if possible.

Regards,

Freddy

Edited by: Freddy Ng on Apr 27, 2011 11:46 AM

View Entire Topic
Former Member
0 Likes

Hi,

you must set "All 1 week" and don't put date on series end.

We have 1 channel with this configuration and it's running fine.