Hi Experts,

Can somebody tells me about T-Code MM50, How can we use it to extend views, secondly, can we use this t-code to extend one material of one plant to another.

Please sugest.

GR

Accepted Solutions (1)

Accepted Solutions (1)

former_member192897
Active Contributor
0 Kudos

MM50 List Extendable Materials Using this Trxn code, You can Extend view to Material Master which is in Bulk.

Let us say you have 100 Materials in Which MRP Views are not maintained. Since it is not possible to go to MM01 and Extend MRP View for Every Material also Its Time taken Job.

For this Scenario, You can use MM50 to Extend MRP View Materials which can be done using LSMW help also.

Regards,

Ashok

Answers (3)

Answers (3)

BijayBarik
Active Contributor
0 Kudos

Hi,

IN MM50, u can extend the material view.( like u can extend General plantdata/Storage-1 view)

For extesion of material from one plant to another plant , check this links :

http://www.copacustomhelp.state.pa.us/infopak/nav/plant%20maintenance/materials/file1192/index.htm

http://www.copacustomhelp.state.pa.us/infopak/nav/procurement/pr%20master%20data/file1434/index.htm

Regards,

Biju K

Former Member
0 Kudos

Go to MM50,

Give Plant and then Execute..

Now, U can see Materials with a Single Alphabet in front of the line.

Select that Icon and Press F4 You can see the Descriptions.

It means that, Those materials doesn't have that view.

So, Check the box, and click on maintain (on application toolbar).

We cannot use this t-code to extend one material of one plant to another

You have to use MM01 Only.

former_member581212
Active Contributor
0 Kudos

yes you can extend of one plant to another...

You can extend via entering material from which you want to extend and to which ...