What are transactions MD04 & MD05. What is difference between data displayed in these two transactions.
Can anybody let me know. I'll reward points.
Thanks & Regards,
Nilesh Kumar
Request clarification before answering.
Hi Nilesh,
to start with after you run MRP, you get MRP List which is static, that is it shows results of MRP only. It will show the same results till you run the next MRP.
Stock Requirement list is Dynamic, this gets updated whenever there is change in status of material. So this list always give you a updated status.
to run MRP, First you have to customize your plant parameters in CBP.
Next you have to select and enter data in MM Record - MRP Views.
You need to have Info Record for the Material / Vendor combination.
You need to have Source list.
then you run the MRP.
Hope this gives a clear flow chart picture.
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 57 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.