on ‎2013 Sep 07 7:32 AM
Dear SAP Experts,
Greetings from Dubai !
I am abrar, working currently under MM- WM Module.
Question: The Ingredients printed on a material ( say bottle) has been changed because of some legal requirements, Since we had created only one material code at the time of initial receipts. Both new and old prints have been entered under the same material code, How to separate the these two variants in sap?
Hope for a quick response !
Regards,
Malik Abrar Altaf
Request clarification before answering.
Thanks all for your valuable suggestions, certainly creating new material code for new prints would be an easy task,but i believe it may create a create a problem for the purchase orders, Because for next year also all purchase orders have been created and sent to supplier in the old material code.
What will happen at the time of creating Inbound deliveries?
Since i am new to SAP MM, i don't have much knowledge about the same.
Hope for some more comments.
Regards,
Abrar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Malik,
just trying to fit in something like jigsaw puzzle.
one way could be creating a new material with old description and assigning it to old material code field in current material master while editing current material text.
henceforth same material will contain reference of both material description. You have not really clarified in your question as if when you want new text and when u want old text to be used.
another method could be using Manufacturing part number , this will allow you to create another 2 material codes which will be assigned as MPN to current material , and you can have 2 different material description at will at the time of procurement.
Please note limitation to both above methods is that any point of time system cannot provide you stock breakup.
warm regards
Avinash
If you go with a new material code creation then you must set the PO line item a deletion flag and insert a new line item in the same Purchase order with the new material code. Like wise if you have any Purchase requisitions open, you will have to do the same thing for PR items also.
Existing stock can be moved with MB1B / MIGO 309 movement type.
| User | Count |
|---|---|
| 30 | |
| 14 | |
| 9 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.