Dear all,
for one materail i am trying to creat PRD order
order type XXXX is mainatined with refernce operation set slection in OPL8
and refernce opration set is already created in CA11
validity is ok
system is throwing following Mssg
while creating PRD order
No default value mainatined for op.generation for order type XXXX (materail YYYYYY)
Regards
kumar
Request clarification before answering.
Kumar,
System is unable to find a valid Referance Operation set, for Production order. Various reasons can be
1. Order quantity not within the Lot Size Validitiy of the Referance Operation set.
2. Referance Operation set "Status" and "usage" problem, not valid or not relevant to production.
3. Referance Operation set must have got created with valid from today, but the order may be exploding the PP-Master data for a past date based on the basic start and finish date of the order.
Please check these parameters...there is no need to maintain OPJG. OPJG should be maintained if you want to allow order creation with default a single operation, in the event of system not able to find a valid routing.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kumar,
The default operation for order type can be maintained in T Code OPJG.
In OPL8,check the task list type (it must be S)and also the routing selection ID,this should allow for the reference operation set
with the highest priority,which can be configured in T Code OPEB.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please check the valdity dates/qty and status of the referance operation set.
You need to select the referance opeartion set during the order creation
Default operation for the plant and order type combination in T Code OPJG.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Brahmankar,
Thanks for ur reply
in OPL8 i have the following settings
1) Application - p
2) selction id - 05
3) Sequence exchange - 0
4) Task List Type - s
5) AltTaskListApplication - blank
6) Routing Selection - 02
7) alternative sequences - checked
😎 Check op. deatils - checked
9) Roting text - checked
Apart from this what should i do
Plz clarify
Regards
kumar
Dear all
Thanks for ur reply
in OPL8 i have the following settings
1) Application - p
2) selction id - 05
3) Sequence exchange - 0
4) Task List Type - s
5) AltTaskListApplication - blank
6) Routing Selection - 02
7) alternative sequences - checked
😎 Check op. deatils - checked
9) Roting text - checked
Reference operation set is valid from is 27.08.09 & valid to 31.12.2009
no deletion flag set
Apart from this what should i do
Plz clarify
Regards
kumar
Edited by: kumar kumar on Sep 14, 2009 2:17 PM
Kumar,
PP-master data would be exploded based on Basic start date of the Order, assuming I have a backlog Planned order or Manually creating an order with Start date as 01.07.2009. In this case system would explode the PP-master data with date as 01.07.2009 and look for valid BOM/Routing/Production versions as on that date. If in your case you have created the Referance routing with valid from today, system would not be able to find this routing.
Regards,
Prasobh
Dear Prasobh,
in OPEB following settings are present
1) selection id - 05
2) SP - 1
3) task list type - S
4) plan usage - 1
5) description - production
Order start date, right now i am trying to creat it, but it's not allowing me
Plz let me know what else is required
As the issue is in Production server
Plz let me know
Regrads
kumar
Edited by: kumar kumar on Sep 14, 2009 2:27 PM
| User | Count |
|---|---|
| 26 | |
| 21 | |
| 19 | |
| 12 | |
| 9 | |
| 9 | |
| 6 | |
| 5 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.