Hi ,
Is anybody have experience on process order blending scenario ?
For example :
We produce 5 different batch finish goods
Now we want to blend those 5 different batch into 1 batch
Thanks for help !
Request clarification before answering.
Hi,
Create process order manually.
Mention the material in Components overview and give the batch numbers of the material which you like to use.
Give the resource and as usual proceed...
for cost information check in the cost tab of the order.
I have followed the same in blending of pharma finished product
regards
Ram Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Here it might also make sense to use a different Process Order type ( eg: blending). This will ensure the visibility/ separate identity for the business of such blending orders v/s normal process orders. I have used different order types for such cases.
Thanks,
Ram Shenoy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 12 | |
| 8 | |
| 6 | |
| 4 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.