Hi experts,

I'm analyzing and studyng PR CO commitment reduction in MM module and I didn't understand the system logical design.

I've created a PR using multiple account assignment for 3 quantities of a specific material as shown below.

The CO commitment has been performed as expected, I mean, one quantity (roughly 3.255,00 BRL) per internal order.

So far, so good 🙂

After that, I've created a PO referencing this PR, but requesting only 2 quantities, as shown below.

After this PO has been posted, I came back to PR and realized the following: Even though my PO is only requesting 2 quantities, using the internal orders 625609 and 625610, the PR commitment reduced in all internal orders (625609, 625610 and 625611).

is the correct system logical design? Shouldn't the commitment be reduced only for internal orders used in PO?

Why the system reduced internal order 625611 if I didn't use it in PO? Is there anyway to modify this behavior or it's the standard design and can't be modified?

Thanks a lot in advanced.

Regards,

Rodrigo Amorim

0 Likes
View Entire Topic
iklovski
Active Contributor

Well, your package is quite advanced, but still there could be issues. For example, look at this note:

2760819 - Incorrect PR commitment update

Regards,

Eli

P.S. Raising OSS message sounds as a good idea.

rodrigo_amorim01
Participant

Thanks a lot Eli,

I'm going to apply this SAP note to verify if the problem will be solved. If it doesn't work, I'm going to raise an oss message to SAP.

As soon as I have any news about that, I'll update this message to let you know the final solution.

Regards,

Rodrigo