Dear All,
Can you guide me with steps through outside processing and subcontracting operation?
It will be appreciate if you guide with configurations and walkthrough steps scenario.
Thank you
Request clarification before answering.
Dear All,
I managed to complete the external/subcontracting
Regarding the raw materials in sub contracting in md04 I can see that the material is at the vendor/subcontractor location.
However, how can I keep track that the Finished Good also went to the vendor/subcontractor and its at his location?
That doesn't happen now.
Please inform if my requirement is correct.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.