Can you guide me with steps through outside processing and subcontracting operation?
It will be appreciate if you guide with configurations and walkthrough steps scenario.
Thank you
Request clarification before answering.
Dear Rafik,
You can do external processing or subcontracting purely from MM perspective or you can trigger the procurement from PP . If you want to trigger the procurement from PP there are two ways . One way by mainatining the procurement key F for external procurement or F 30 for sub-contracting and during MRP run system directly generates PR for the requirement.
In the second ,you can use a control key PP02 for a dummy operation and assigning the material to that operation with all the purchase related information . In this case the release of the production order generates a PR for that material.
Once the PR generated , MM people will convert it to PO , issue raw material or semi finished material against sub-contracting PO using 541.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 13 | |
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.