Hi Experts,

Is there any mass processing T.Code by which I can read all the PP master data for production orders collectivily?

0 Likes
View Entire Topic
rupesh_brahmankar
Active Contributor
0 Likes

Dear,

Not possible.

Best way active the TECo and run MRp again with planning mode-3 delted and recreated then onvert the planned order to prodution order it will update all value.

Regards,

R.Brahmankar

Former Member
0 Likes

I agree with you but my case is that I had already converted the planned orders into production orders and I chabged the control key in a routing for some improvement but I also cannot delete that production orders which has already been made and in some case partial confirmation has also been done.

So is there any alternative so that I should not teco or delete the existing production order and reflect my new control key in those orders. I can do it manually by CO02 but it is consuming time as I have 5000 production orders.

dhaval_choksi3
Active Contributor
0 Likes

Hi Deepak,

As our Other expert has told there is no Mass Facility is there for doing Read Master Data.And as you told if any transactions are already done then it becomes more difficult for you to do Read Master Data Manually.

But do one thing do similar changes in your earlier Control Key itself , it will effect running orders also.Then from new order onwards use new Control key (as you have already change the Routing)