on ‎2015 Jul 03 1:01 PM
Dear Experts,
Could you please help me in finding a best solution for the below two scenarios?
I'm aware that we can use material to material transfer (mvt type 309) process to downgrade a material, but here the quantity will not be varying, meaning, if i transfer 2 MT from material A to material B, material B will be receiving the same quantity i.e. 2 MT. But how can we capture increase / decrease of quantity while downgrading?
Kindly help me to implement a best solution.
Thanks & Regards,
Pavithra
Request clarification before answering.
SAP can't change any quantity itself. Even it is a damaged material, quantity should not be changed during material transfer ?
It may be possible from a business points of view (weight can increase or decrease due to moisture), but SAP will never accept that.
You need to perform 201 or 202 movement type (or similar, as per your requirement) after transfer posting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you know the movements?
201 is remove quantity, 202 a reversal movement that adds quantity.
there is no link between those 2 movements, there is no reference for these movements.
So you can issue with 201 from A as much as you want, and add with 202 to B as much as you want. A value difference remains at the cost center.
because it is the only way to have different quantities for decrease and increase of quantity which is not possible with 309. And if you allow external value for the movement 202, then you can even enter the same value that was issued before with the 201 movement and you would not get any value difference that remains at the cost center.
| User | Count |
|---|---|
| 23 | |
| 13 | |
| 10 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.