Hi..

i have one finish material , which having five operation. Out of five third operation (Op.30) is external processing operation . Finish material use "metal rod "as a raw material.

After creation of production order system has cretaed PR for third operation.

Now I issued the" metal rod " for the first and second operation . After processing , third operation is External Processing,but my store person not getting the material in stock .Asi issued the metal rod for start the operation.

How should i deal with this condition.

What componenets i should maintain in routing of finish material.How store peson get the stock of material.

What is ideal case fro external process operation ??

Plasehelp out

Thnks

0 Likes
View Entire Topic
Former Member
0 Likes

WHy dont you just create an intermediate material send it for external operation. In this scenario , you can get a new material after 1st two operation , then you can issue this material as component for the next material having the external operation , then receive this external processed material & do the remaining operations to get your finished material . This would be a much simpler approach and more easier to generate reports.

Former Member
0 Likes

Thnks for ur reply..

But i dont want to create a intermediate material..as it will be tedious and bulky master for my process.

How is the ideal scenario ??

In my case what i have to do ????